Ariana Resources is targeting a final investment decision on its Dokwe gold project in Zimbabwe in the second half of 2027, with commissioning planned a year later as the company advances feasibility work and prepares to approach lenders for project financing, Mining Zimbabwe can report.
By Ryan Chigoche
Responding to questions from Mining Zimbabwe, Ariana Resources Chief Executive Dr Kerim Sener said the company expects to complete the major technical components of its Definitive Feasibility Study (DFS) during the fourth quarter of 2026 and first quarter of 2027.
Metallurgical test work is underway in China with Xinhai Mining Services and in Australia with IMO, while specialist consultancies are working on the mineral resource estimate, mining, water, power and environmental components of the study.
Ariana is also drilling to complete the sterilisation pattern in areas earmarked for infrastructure, assessing whether planned facilities could overlap with mineralised ground. Separate water bore drilling is testing an aquifer identified as a potential source of process water.
The technical programme is expected to provide the foundation for financing discussions, although completing the studies will not automatically trigger a final investment decision.
Ariana plans to engage financial institutions once the technical work is complete, with lenders expected to undertake independent due diligence and potentially require further investigations before approving funding.
“Following completion of the technical works associated with the feasibility study, we will be actively engaging with financial institutions with respect to the planned project finance to develop Dokwe,” Sener said.
That process could extend the time needed to finalise the DFS, as financing institutions assess the assumptions, technical parameters and risks underpinning the proposed development.
“It is likely that these institutions will require time for their own due diligence and potentially require us to complete additional work on aspects of the feasibility,” he said.
Sener described the DFS as a potential “moving feast”, saying its final form would depend on lenders being satisfied that their requirements had been met.
Ariana is seeking to limit that risk by completing the technical programme to the highest possible standards and anticipating additional information that financiers may require.
The company expects construction to take about a year once financing is secured. If it reaches a final investment decision in the second half of 2027, Dokwe could enter commissioning in the second half of 2028.
The financing process therefore represents a critical step in translating the project’s feasibility work into a construction commitment.
Dokwe is Ariana’s flagship gold development in Zimbabwe. An updated pre-feasibility study released earlier this year estimated its pre-tax net present value at US$1.06 billion, based on projected production of 1.06 million ounces over a 20-year mine life.
The project is designed to reach peak annual production of about 100,000 ounces, with pre-production capital expenditure estimated at US$164 million.