Mutapa Gold Resources’ Nine-Month Profit Jumps 200% as Gold Output Rises

Published:

Mutapa Gold Resources’ profit after tax rose 200% to US$156 million in the nine months to September 2026, as higher gold prices and increased production lifted earnings at the state-owned mining group, Mining Zimbabwe can report.

By Rudairo Mapuranga

Revenue for the nine-month period increased 63% to US$402 million from US$246 million in the same period last year, while earnings before interest, tax, depreciation and amortisation (EBITDA) rose 133% to US$231 million from US$99 million.

Chief executive Patrick Maseva-Shayawabaya said the financial results reflected the group’s stronger operational performance and the higher gold prices realised during the period.

“The financial performance of the company mirrored the operational performance and also the fact that the gold price realised for the three months and for the nine months was higher than for the equivalent period last year,” he said.

Gold production increased 16% to 89,639 ounces in the nine months to September, compared with 77,415 ounces a year earlier. Quarterly output rose 14% to 30,116 ounces from 26,405 ounces, despite a 6% decline in ore milled.

The group’s average realised gold price rose 22% to US$4,211 an ounce in the third quarter, from US$3,440 in the corresponding period last year.

Quarterly revenue increased 39% to US$127 million, while EBITDA rose 58% to US$67 million. Profit before tax climbed to US$61 million from US$34 million, and profit after tax increased 57% to US$45 million from US$29 million.

Maseva-Shayawabaya attributed the production gains to improved head grades and recovery rates, supported by better grade-control practices and investment in processing infrastructure.

Quarterly head grade improved to 1.50 grammes per tonne from 1.32 g/t, while the recovery rate rose to 86% from 83%.

“At Freda, we also looked at abandoning some stopes that were perhaps unsafe and opened new stopes,” he said, explaining the measures taken to improve grades at Freda Rebecca Gold Mine.

On recovery, he pointed to the commissioning of additional leach tanks at the group’s operations.

“We invested in three leach tanks at Fred and we also invested in four leach tanks at Jena,” he said.

The additional tanks improved residence time, allowing more time for the extraction process. The group’s ore-milling performance was affected by Freda Rebecca’s Mill Number One being offline for 23 days in August for a long-planned shell replacement.

Despite cost pressures, cash costs remained broadly stable at US$1,569 an ounce, compared with US$1,562 in the prior-year quarter. All-in sustaining costs rose 13% to US$2,337 an ounce, mainly because of higher sustaining capital expenditure and royalties.

Shamva Hill Project Backed by US$160m Facility

Mutapa has started implementing its Shamva Hill project, which is expected to be completed by December 2028 at a cost of US$240 million.

The project involves developing a 2.4-million-tonne open-pit mine and processing plant and is expected to increase annual gold production from 25,000 ounces to approximately 80,000 ounces.

Maseva-Shayawabaya said the group had secured US$160 million from local banks to cover the project’s requirements until around September 2027, by which time it expects to conclude negotiations with external financiers.

The syndicated loan facility has increased from an initial US$110 million, with drawdowns already underway.

The group is also advancing the Jena Mines Phase One expansion, which aims to raise annual production from 15,000 ounces to approximately 40,000 ounces. The project is expected to commence in the second quarter of 2027, following completion of exploration drilling and scoping studies.

Exploration Targets Resource Upgrades

Mutapa had completed approximately 88,000 metres of diamond drilling by the end of September against a programme target of about 198,000 metres.

The company expects a major resource upgrade at Freda Rebecca in the first quarter of 2027, followed by an updated resource estimate for Jena Mines in the latter part of the year.

Maseva-Shayawabaya said exploration was essential to improving the group’s understanding of its mineral resources and supporting future mine planning.

Output Forecast Set to Exceed 110,000 Ounces

Mutapa expects full-year gold production to exceed its previous forecast of 110,000 ounces, following output of 89,639 ounces in the first nine months.

However, the company expects revenue and profitability to remain in line with its previous forecasts as lower gold prices offset the benefit of higher production.

“We are pretty confident that we will exceed the previous forecast of 110,000 ounces,” Maseva-Shayawabaya said.

The group reported one fatality in the nine months to September and one lost-time injury during the third quarter. The chief executive said the fatal incident at Jena Mines was avoidable and that the company continued to strengthen critical safety controls.

Mutapa also reported community investments, including a US$3 million water pipeline project undertaken with Bindura Municipality and a maternity ward under construction at Bindura Hospital, expected to cost approximately US$700,000.