Zimbabwe’s 59-Tonne Gold Ambition Faces Royalty Test

Published:

Zimbabwe’s ambition to increase gold deliveries towards 59 tonnes in 2027 is exposing a growing tension between the industry’s expansion plans and the fiscal conditions under which mining companies must operate, with large-scale producers calling for a review of the country’s gold royalty structure, Mining Zimbabwe can report.

 

By Rudairo Mapuranga

The latest State of the Mining Industry Survey Report, presented by Professor Albert Makochekanwa, projects national gold output to increase from an estimated 55 tonnes in 2026 to 59 tonnes next year, supported by higher capital expenditure, improved operating capacity and continued expansion across the sector.

However, the outlook is accompanied by concerns over royalty charges, electricity costs and financing conditions, which mining executives say could undermine the viability of projects despite favourable international gold prices.

The royalty question is particularly significant as Zimbabwe seeks to attract fresh investment into existing operations while encouraging producers to expand their contribution to national output.

Gold expansion backed by US$400 million investment

The survey identifies large-scale gold producers as an important source of the anticipated production increase, with approximately US$400 million budgeted for expansion projects intended to lift national gold output from the projected 55 tonnes in 2026 to 59 tonnes in 2027.

All gold-sector executives who participated in the survey reportedly indicated intentions to expand their operations and increase capital expenditure next year.

Gold-sector capacity utilisation is also projected to increase from 91% in 2026 to 96% in 2027, reflecting expectations of higher operating activity across existing mining operations.

The planned investment comes against a backdrop of sustained growth in formal gold deliveries.

Zimbabwe delivered 46,729.06 kilogrammes of gold to Fidelity Gold Refinery (FGR) in 2025, compared with 36,486.75kg in 2024, representing a 28.1% increase.

The momentum has continued into 2026. By the end of October, deliveries had reached approximately 41.4 tonnes, according to Fidelity figures, with small-scale and artisanal miners contributing 30.05 tonnes and primary producers accounting for 11.34 tonnes.

The October deliveries of 5.52 tonnes were the highest monthly total recorded during the first ten months of the year.

These figures demonstrate the importance of both established mining houses and smaller producers in sustaining national gold supply.

Nevertheless, the difference between the 2027 industry projection and Fidelity’s separately announced 55-tonne delivery target highlights the need to distinguish between production ambitions and the formal gold mobilisation target.

Royalty structure emerges as investment concern

Despite the positive production outlook, the survey identifies the fiscal environment as a significant concern for mining executives, particularly the royalty structure introduced on 1 January 2026.

Under the current sliding-scale framework, gold royalties are charged at 3% when prices are below US$1,200 per ounce, 5% when prices are above US$1,200 and up to US$5,000, and 10% when prices exceed US$5,000 per ounce.

Large-scale producers are seeking a review of how the higher royalty threshold is applied.

Their concern centres on the application of the 10% rate once the international gold price exceeds US$5,000 per ounce. They want the higher rate to apply only to the incremental value above that threshold rather than the entire value of the gold sale.

The distinction is financially significant.

Under an incremental approach, the higher rate would apply only to the additional value generated above US$5,000 per ounce, rather than triggering a higher royalty calculation across the entire sale value.

For producers operating capital-intensive mines, the difference could influence operating margins, investment returns and decisions on whether to proceed with expansion projects.

The industry is therefore seeking a royalty framework that allows Government to benefit from higher international prices without creating a fiscal burden that could discourage additional production.

The concern also comes as mining executives identify electricity tariffs, financing costs and other statutory charges as major pressures on project viability.

According to the survey, Zimbabwean miners are paying approximately USc14.21 per kilowatt-hour for electricity, against a regional average of USc7.80.

This places local mining operations at a considerable cost disadvantage, particularly for producers whose operations depend on energy-intensive crushing, milling, pumping and processing activities.

The royalty debate is consequently part of a wider discussion about Zimbabwe’s competitiveness as a mining investment destination.

Small-scale miners remain central to production growth

While large-scale producers are expected to contribute through capital-intensive expansion projects, Zimbabwe’s gold production trajectory remains heavily dependent on artisanal and small-scale miners.

In 2025, small-scale producers delivered 34,875.10kg of gold to Fidelity, against national deliveries of 46,729.06kg.

This represented approximately 74.6% of total national deliveries, demonstrating the extent to which the country’s gold industry depends on smaller operators.

The contribution remained substantial in 2026.

By October, small-scale miners had delivered 30.05 tonnes, accounting for approximately 72.6% of national gold deliveries.

The survey identifies access to affordable capital, mining equipment, geological information and formal marketing channels as important requirements for sustaining growth in this segment.

It also highlights opportunities for stronger collaboration between small-scale miners and established mining companies through equipment support, technical assistance, safer mining practices and tributing arrangements.

Such partnerships could improve productivity while helping smaller operators access the technical and financial resources required to develop their claims.

Fidelity Gold Refinery is also pursuing measures to improve formal gold mobilisation through its Gold Development Initiative Fund (GDIF).

FGR’s Francis Maidza said the funding programme had supported almost 3,300 miners by the end of 2025.

The refinery is also introducing an ASM Gold Card and strengthening responsible sourcing and traceability systems to improve the formalisation of small-scale gold production.

These interventions are important because increasing actual mining output is only part of the challenge. Ensuring that gold enters formal marketing channels is equally important for the country’s foreign currency earnings and the effectiveness of its gold mobilisation strategy.

Production ambitions face a competitiveness test

Zimbabwe’s 2027 gold outlook comes at a time when the Government is seeking to increase mineral production, attract investment and expand the mining sector’s contribution to the economy.

The industry-wide survey projects mining revenues to increase from an estimated US$13.6 billion in 2026 to US$14.6 billion in 2027, while formal mining employment is expected to grow by 3% to approximately 62,000 workers.

However, the gold sector’s ability to achieve its ambitions will depend on more than favourable international prices and announced expansion budgets.

The planned US$400 million investment in large-scale gold operations, continued small-scale mining growth and improvements in formal gold marketing will all need to translate into actual production and deliveries.

At the same time, the industry’s concerns over royalties, electricity tariffs and financing costs present policy questions that Government must address as it seeks to attract and retain mining capital.

The distinction between a production forecast and an achievable investment-backed target will ultimately be determined by whether the operating environment allows mining companies to commit capital, expand capacity and sustain production.

For Zimbabwe, the challenge is no longer simply mobilising more gold. It is creating the fiscal, financial and operational conditions necessary to sustain production growth while ensuring that the country captures an appropriate return from its mineral resources.