Zimbabwe’s coal producers have called for commercially viable domestic coal pricing, predictable payments from the Zimbabwe Power Company (ZPC), continued access to export markets and improved transport infrastructure, warning that the current operating environment could undermine investment and the country’s broader coal beneficiation ambitions, Mining Zimbabwe can report.
By Rudairo Mapuranga
Raymond Mutokonyi, director of Makomo Resources and representative of coal producers, said the proposed mining policy framework should balance the government’s value-addition objectives with the commercial realities of coal production, including differences in product quality, market requirements and the costs of transporting the mineral.
Presenting the producers’ position during consultations on the proposed mining policy framework, Mutokonyi said ZPC, currently Makomo’s largest coal customer, remained an important domestic market but that prevailing supply arrangements presented significant commercial challenges.
“There must be parity in terms of price, as well as the volumes to the local industry,” Mutokonyi said.
He noted that although ZPC is Zimbabwe’s largest consumer of thermal coal, the approximately eight coal producers in the country do not necessarily enjoy equal treatment in terms of supply volumes and prices.
He argued that producers supplying coal of equivalent quality should receive comparable prices, citing differences between supplies to Units 1 to 6 and Units 7 and 8 at Hwange Power Station.
“For the same quality of coal, it should have a similar price,” he said.
Payment delays were another major concern, with Mutokonyi saying producers could wait more than six months for payments despite having supplied coal already consumed by the power utility.
He said outstanding amounts could run into millions of US dollars, creating cash-flow pressures and making it difficult for companies to meet operational obligations.
“If we know that you’ll pay after six months, then we’ll plan accordingly,” he said, calling for clearly defined payment timelines that would allow producers to manage their businesses without repeatedly pursuing outstanding payments.
Export flexibility needed during beneficiation transition
Beyond domestic pricing and payment arrangements, coal producers are seeking continued access to raw coal export markets while economically viable beneficiation capacity is developed.
In their policy submissions, producers argued that beneficiation should be encouraged through investment incentives rather than compulsory export restrictions that could limit access to alternative markets before local processing facilities are commercially established.
Mutokonyi said the government should clearly define the proportion of production required by the domestic market and allow surplus coal to be exported, enabling companies to plan production and marketing strategies.
He cautioned that producers needed certainty over domestic supply requirements, particularly given the characteristics of coal once it has been extracted.
The producers also argued that coal quality, product specifications and market requirements should inform beneficiation policies, as not all coal deposits are suitable for the same processing applications.
They proposed a phased approach that maintains export opportunities while encouraging investment in washing plants, coke production and other economically viable downstream activities.
Mutokonyi said beneficiation should recognise different levels of value addition rather than impose identical expectations across the industry.
Coal washing can improve product quality by removing impurities, while suitable coking coal can undergo further processing into metallurgical coke for industrial applications.
However, he cautioned against expecting every coal producer to establish similar downstream facilities, particularly power generation projects.
Producers warn against duplication of power projects
Mutokonyi questioned the sustainability of an approach where every coal producer independently pursues power generation as its preferred beneficiation route.
Using the possibility of 15 companies establishing 15 power stations in the same area as an illustration, he questioned whether such developments would be commercially and environmentally sustainable over the longer term.
He argued that the government should determine the appropriate number and type of beneficiation projects in particular areas, taking into account available resources, production requirements and future market demand.
“There are some commodities that you cannot benefit beyond washing, for example. So we all can’t produce power stations or create power stations,” he said.
His concerns find common ground with those expressed by ZPC Acting Managing Director Engineer Fannie Mavhondo, who has also called for coordinated planning of coal-fired power generation investments.
Speaking at the Chamber of Mines Annual Conference’s coal, oil and gas symposium, Mavhondo said the government needed to determine how many coal power stations should be developed, their generation capacities and the availability of electricity buyers.
He warned that limiting ZPC’s coal purchases to a few producers could encourage other mining companies to establish independent power generation projects, potentially creating an imbalance between electricity supply and demand.
“If we are to survive, if we said ZPC only takes from two or three miners, it means the rest may want to go into coal power plants as well or any other alternative. So you may see a boom again on the other side, which creates a deficit on the other,” Mavhondo said.
He called for government-level planning to establish how many coal stations and other specialised power plants should be developed, how much electricity they should generate and where the power would be purchased.
The two contributions highlight the importance of coordinating coal production, beneficiation investments and electricity generation rather than allowing projects to develop independently without sufficient consideration of market requirements.
Transport infrastructure constrains alternative markets
Coal producers also identified deteriorating road and rail infrastructure around Hwange as a major constraint to accessing alternative domestic and regional markets.
In their submission, they said coal mining was a high-volume, logistics-intensive business whose commercial viability depended heavily on the availability, reliability and cost of transportation.
Inadequate rail capacity has increased dependence on road haulage, raising transport costs, reducing competitiveness and accelerating the deterioration of road infrastructure.
The producers argued that these challenges were particularly damaging when companies needed alternative markets to compensate for commercially unsustainable domestic supply arrangements.
They warned that policies promoting increased production and beneficiation without corresponding investment in transport infrastructure risk creating additional productive capacity without commercially viable routes to market.
The government was urged to prioritise the rehabilitation and modernisation of strategic coal transportation corridors, particularly the Hwange-Bulawayo road and National Railways of Zimbabwe (NRZ) infrastructure.
The infrastructure concerns come as major producers seek to expand output and access regional markets.
Hwange Colliery Company Limited (HCCL) has outlined capacity to produce up to 15 million tonnes of coal annually, although actual production is expected to reach approximately seven million tonnes in the current financial year before increasing to 10 million tonnes the following year.
HCCL Administrator Munashe Shava has identified markets and logistics as the company’s principal constraints, indicating that increased extraction capacity must be matched by reliable transport and sufficient demand.
The company resumed metallurgical coke production in July 2026 following an US$8 million rehabilitation of its coke oven battery, which had been dormant since 2014.
The facility is expected to reach production of 600 tonnes of coke daily at full capacity, creating opportunities to move further up the coal value chain.
HCCL is also considering four additional coke oven batteries over the next five years, alongside opportunities to commercialise by-products from the coking process.
Fiscal burden raises investment concerns
The coal producers also raised concerns over the cumulative fiscal burden facing the industry, arguing that existing charges are eroding profitability and limiting the capacity of companies to invest in expansion and beneficiation.
The charges identified in their submission include the 3% levy applicable to coal exports, the 1% mining royalty and Minerals Marketing Corporation of Zimbabwe (MMCZ) commissions and related marketing charges.
These costs come alongside corporate taxation, statutory fees, regulatory expenses, a 30% compulsory liquidation requirement and high operating costs associated with deteriorating infrastructure.
The producers argued that the combined burden could weaken the competitiveness of Zimbabwean coal and discourage investment in processing facilities.
They called for a more competitive and predictable fiscal framework that recognises the capital requirements of beneficiation projects and the commercial pressures facing producers.
The concerns come as the government seeks to attract further investment into the sector, with Mines and Mining Development Minister Dr Polite Kambamura announcing plans to classify metallurgical coal as a special critical mineral to encourage investment and downstream industrial development.
The proposed policy change is expected to support investment in coal processing and related industries, although producers argue that the fiscal and regulatory environment must also make such investments commercially viable.
Coal remains central to energy security
Zimbabwe’s coal industry generated US$194.3 million in export earnings during the first nine months of 2026, with September sales rising 38% above the monthly average.
Beyond exports, coal remains an important component of the country’s energy mix, supplying Hwange Power Station and providing feedstock for industrial processes, including metallurgical coke production.
Mavhondo said ZPC’s assessments indicate that Zimbabwe has sufficient coal resources to sustain power generation for more than 200 years, with further exploration continuing.
“Our numbers show that we believe over 200 years of mining are still with us in terms of the availability of the resource,” he said.
Hwange Power Station’s Units 7 and 8 added a combined 670 megawatts of installed generation capacity, while a US$450 million rehabilitation agreement with Jindal Steel and Power is expected to restore approximately 400MW from the ageing Units 1 to 6 within 48 months.
Mavhondo maintained that coal and renewable energy should complement each other, arguing that reliable baseload generation remained important for an industrialising economy.
The coal producers’ submissions therefore come at a time when Zimbabwe is seeking to expand electricity generation, increase mineral beneficiation and develop additional industrial uses for its coal resources.
They argue that achieving these objectives will require more than production targets and restrictions on raw mineral exports.
In their proposed policy position, producers urged the government to adopt a balanced framework that prioritises commercially viable domestic coal pricing, payment security, improved transportation infrastructure, a competitive fiscal regime and continued access to export markets.
The central argument is that beneficiation must be supported by the commercial conditions, infrastructure and market access required to sustain investment, rather than becoming an obligation that compromises the viability of existing coal operations.